One request, followed all the way to production

  • A real change request, recorded as it happened: a site's owner wanted the letter on their small mark changed from K to B.
  • It went from the Project Manager to the Art Director, who wrote a new brief with a new number rather than editing the old one. The Owner generated the image. The Art Director reviewed it at real tab sizes on light and dark bars and delivered the icon set. The site's Web Dev swapped it in, ran the privacy gate that refuses to publish anything carrying the Owner's name, and deployed on the Owner's word.
  • Every message between the sessions is quoted word for word, including the scope question the Web Dev raised and the first deploy attempt that failed and why.
  • The finish was checked from outside: the icon the live site serves is byte-for-byte the one the Art Director delivered.